Roads being paved in 2021
The following roads will be paved in 2021:
- 9th Line from Industrial Park Road to Bowman Street
- 9th Line from 20th Sideroad to Leonard Street
- 20th Sideroad from Shore Acres Drive to the Town's Southern Boundary
This project has been awarded and work is scheduled to begin mid-May 2021 with completion scheduled for in Fall 2021. The Town will update once the schedule and sequencing is known. Notices to Residents will be sent out once the construction schedule is confirmed by the contractor.
The following roads are in the design phase and are scheduled to be rehabilitated in 2021:
- 5th Line from Yonge Street to Lot 7/8 (West of 10th Sideroad)
- 9th Line from 20th Sideroad to Yonge Street
- 10th Line from Yonge Street to 10th Sideroad
- Gilford Road from 20th Sideroad to Beach Road North
Once the Contractor's schedule is known, Notices to Residents will be sent out prior to the work beginning along with any additional information.